← Meridian Builders
Application 1
Coral Bay Surgical Center · C-CBS-2405-05 · period ending Dec 8, 2025 · PaidCompleted to date
$900,037
Stored materials
$0
Retainage withheld
$90,004
Retainage required
$90,004
Due this application
$810,034
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | — | $68,093 | $68,093 | — | 2% | $6,809 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | — | $0 | $0 | — | 0% | $0 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | — | $0 | $0 | — | 0% | $0 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | — | $0 | $0 | — | 0% | $0 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | — | $426,432 | $426,432 | — | 8% | $42,643 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | — | $43,774 | $43,774 | — | 2% | $4,377 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | — | $0 | $0 | — | 0% | $0 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | — | $0 | $0 | — | 0% | $0 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | — | $0 | $0 | — | 0% | $0 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | — | $269,326 | $269,326 | — | 8% | $26,933 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | — | $92,412 | $92,412 | — | 2% | $9,241 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | — | $0 | $0 | — | 0% | $0 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | — | $0 | $0 | — | 0% | $0 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $0 | $900,037 | $900,037 | $0 | 2% | $90,004 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app01.pdf p.1 of 14 | — | Dec 11, 2025 |
| conditional_waiver | waiver_cond_app01.pdf p.1 of 1 | — | Dec 14, 2025 |
| unconditional_waiver | waiver_uncond_app01.pdf p.1 of 1 | — | Jan 19, 2026 |