Drawcheck

Draw review

$31M in this month’s pay applications does not survive the arithmetic.

Drawcheck recomputes every schedule-of-values line against the approved change orders, the retainage terms in the contract, the supporting documents attached to the draw, and an independent observation of physical progress. It reports the two numbers it compared and where each came from.

Exceptions open

11

5 critical

Amount at issue

$31M

across all draws under review

Contracts

7

4 projects

Contract value

$376M

adjusted for approved changes

Contracts under review

ContractProjectAdjusted valueBilled to date% billed% observedExceptionsAt issue
Vantage Construction Group
C-BRK-2201-01 · draw 14
Brickell Bay Tower$151,697,001$137,714,44590.8%76.7% +141C 1H$26,531,408
Meridian Builders
C-WYN-2304-03 · draw 12
Wynwood Yards Mixed Use$72,578,477$64,885,10789.4%89.1%1H$3,052,157
Cordova Glass Systems
C-BRK-2201-02 · draw 14
Brickell Bay Tower$24,628,027$23,313,67594.7%95.2%1C 1H$541,979
Meridian Builders
C-CBS-2405-05 · draw 10
Coral Bay Surgical Center$58,990,009$53,585,30590.8%89.6%2C $492,240
Delmar Mechanical
C-WYN-2304-04 · draw 12
Wynwood Yards Mixed Use$15,296,515$13,452,83887.9%90.0%2H$149,000
Keystone Contracting
C-AVL-2312-07 · draw 13
Aventura Logistics Park$43,022,768$38,440,33789.3%89.8%1C $88,830
Everglade Electric
C-CBS-2405-06 · draw 10
Coral Bay Surgical Center$10,224,938$8,827,53586.3%89.6%$55,991

Largest exposures

All exceptions →
CriticalBILLING-AHEAD-OF-PROGRESSVantage Construction GroupBrickell Bay Tower$21,298,259

Application 14 bills 90.8 percent of the adjusted contract against an observed 76.7 percent complete on Aug 27 2026

claimed 90.8%supported 76.7%application 14
CriticalOVERBILL-LINECordova Glass SystemsBrickell Bay Tower$431,063

Line 2 (Structural steel) is billed to $5,220,646 against an adjusted scheduled value of $4,789,583

claimed $5,220,646supported $4,789,583application 14
CriticalOVERBILL-LINEMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 (General conditions) is billed to $4,348,120 against an adjusted scheduled value of $4,102,000

claimed $4,348,120supported $4,102,000application 10
CriticalCO-UNAPPROVED-BILLEDMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 is billed $246,120 above its base value while change orders totalling $215,694 on this line are still unapproved

claimed $4,348,120supported $4,102,000application 10
CriticalINVOICE-REUSEDKeystone ContractingAventura Logistics Park$88,830

Supplier invoice invoice_glazing_4471.pdf appears on applications 2 and 3 for the same amount

claimed invoice_glazing_4471.pdfsupported one applicationapplication 3