Drawcheck
Meridian Builders

Application 3

Coral Bay Surgical Center · C-CBS-2405-05 · period ending Feb 6, 2026 · Paid

Completed to date

$4,545,045

Stored materials

$222,680

Retainage withheld

$476,773

Retainage required

$476,773

Due this application

$2,579,803

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,102,000$4,102,000$217,406$323,648$541,05413%$54,105
202-200Sitework and excavation$3,223,000$343,388$3,566,388$0$231,734$231,7347%$23,173
303-300Concrete, foundations$5,274,000$5,274,000$0$62,761$62,7611%$6,276
403-330Concrete, superstructure$8,790,000$8,790,000$0$0$00%$0
505-100Structural steel$5,567,000$5,567,000$629,071$439,236$1,068,307$222,68019%$129,099
607-500Roofing and waterproofing$2,637,000$2,637,000$139,761$208,059$347,82013%$34,782
708-400Curtain wall and glazing$7,032,000$7,032,000$0$505,601$505,6017%$50,560
809-250Drywall and framing$4,102,000$4,102,000$0$48,814$48,8141%$4,881
909-650Flooring and finishes$3,223,000$3,223,000$0$0$00%$0
1015-400Plumbing$3,516,000$3,516,000$397,308$277,412$674,72019%$67,472
1115-700HVAC$5,567,000$5,567,000$295,051$439,236$734,28713%$73,429
1216-100Electrical$4,395,000$4,395,000$0$316,001$316,0017%$31,600
1321-100Fire protection$1,172,000$46,621$1,218,621$0$13,947$13,9471%$1,395
Totals$58,600,000$390,009$58,990,009$1,678,597$2,866,448$4,545,045$222,6808%$476,773

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 12Feb 9, 2026
conditional_waiverwaiver_cond_app03.pdf p.1 of 1Feb 12, 2026
supplier_invoiceinvoice_app03.pdf p.1 of 2$123,060Feb 10, 2026
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1Mar 20, 2026