← Meridian Builders
Application 4
Coral Bay Surgical Center · C-CBS-2405-05 · period ending Mar 8, 2026 · PaidCompleted to date
$12,593,140
Stored materials
$0
Retainage withheld
$1,259,314
Retainage required
$1,259,314
Due this application
$7,042,873
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | $541,054 | $603,814 | $1,144,868 | — | 28% | $114,487 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | $231,734 | $474,426 | $706,159 | — | 20% | $70,616 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | $62,761 | $776,333 | $839,093 | — | 16% | $83,909 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | $0 | $871,089 | $871,089 | — | 10% | $87,109 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | $1,068,307 | $819,462 | $1,887,770 | — | 34% | $188,777 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | $347,820 | $388,166 | $735,987 | — | 28% | $73,599 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | $505,601 | $1,035,110 | $1,540,711 | — | 22% | $154,071 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | $48,814 | $603,814 | $652,628 | — | 16% | $65,263 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | $0 | $319,399 | $319,399 | — | 10% | $31,940 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | $674,720 | $517,555 | $1,192,276 | — | 34% | $119,228 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | $734,287 | $819,462 | $1,553,750 | — | 28% | $155,375 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | $316,001 | $646,944 | $962,945 | — | 22% | $96,294 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | $13,947 | $172,518 | $186,465 | — | 15% | $18,647 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $4,545,045 | $8,048,095 | $12,593,140 | $0 | 21% | $1,259,314 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app04.pdf p.1 of 5 | — | Mar 11, 2026 |
| conditional_waiver | waiver_cond_app04.pdf p.1 of 1 | — | Mar 14, 2026 |
| unconditional_waiver | waiver_uncond_app04.pdf p.1 of 1 | — | Apr 19, 2026 |