← Meridian Builders
Application 6
Coral Bay Surgical Center · C-CBS-2405-05 · period ending May 7, 2026 · PaidCompleted to date
$37,310,620
Stored materials
$0
Retainage withheld
$3,731,062
Retainage required
$3,731,062
Due this application
$11,122,866
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | $2,009,980 | $865,112 | $2,875,092 | — | 70% | $287,509 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | $1,385,890 | $679,731 | $2,065,621 | — | 58% | $206,562 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | $1,951,380 | $1,112,287 | $3,063,667 | — | 58% | $306,367 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | $2,724,900 | $1,853,811 | $4,578,711 | — | 52% | $457,871 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | $3,061,850 | $1,174,080 | $4,235,930 | — | 76% | $423,593 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | $1,292,130 | $556,143 | $1,848,273 | — | 70% | $184,827 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | $3,023,760 | $1,483,049 | $4,506,809 | — | 64% | $450,681 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | $1,517,740 | $865,112 | $2,382,852 | — | 58% | $238,285 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | $999,130 | $679,731 | $1,678,861 | — | 52% | $167,886 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | $1,933,800 | $741,524 | $2,675,324 | — | 76% | $267,532 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | $2,727,830 | $1,174,080 | $3,901,910 | — | 70% | $390,191 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | $1,889,850 | $926,906 | $2,816,756 | — | 64% | $281,676 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | $433,640 | $247,175 | $680,815 | — | 56% | $68,081 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $24,951,880 | $12,358,740 | $37,310,620 | $0 | 63% | $3,731,062 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app06.pdf p.1 of 12 | — | May 10, 2026 |
| conditional_waiver | waiver_cond_app06.pdf p.1 of 1 | — | May 13, 2026 |
| unconditional_waiver | waiver_uncond_app06.pdf p.1 of 1 | — | Jun 18, 2026 |