← Meridian Builders
Application 7
Coral Bay Surgical Center · C-CBS-2405-05 · period ending Jun 6, 2026 · PaidCompleted to date
$45,936,540
Stored materials
$0
Retainage withheld
$4,593,654
Retainage required
$4,593,654
Due this application
$7,763,328
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | $2,875,092 | $603,814 | $3,478,906 | — | 85% | $347,891 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | $2,065,621 | $474,426 | $2,540,046 | — | 71% | $254,005 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | $3,063,667 | $776,333 | $3,839,999 | — | 73% | $384,000 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | $4,578,711 | $1,293,888 | $5,872,599 | — | 67% | $587,260 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | $4,235,930 | $819,462 | $5,055,393 | — | 91% | $505,539 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | $1,848,273 | $388,166 | $2,236,440 | — | 85% | $223,644 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | $4,506,809 | $1,035,110 | $5,541,919 | — | 79% | $554,192 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | $2,382,852 | $603,814 | $2,986,666 | — | 73% | $298,667 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | $1,678,861 | $474,426 | $2,153,286 | — | 67% | $215,329 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | $2,675,324 | $517,555 | $3,192,880 | — | 91% | $319,288 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | $3,901,910 | $819,462 | $4,721,373 | — | 85% | $472,137 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | $2,816,756 | $646,944 | $3,463,700 | — | 79% | $346,370 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | $680,815 | $172,518 | $853,333 | — | 70% | $85,333 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $37,310,620 | $8,625,920 | $45,936,540 | $0 | 78% | $4,593,654 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app07.pdf p.1 of 13 | — | Jun 9, 2026 |
| conditional_waiver | waiver_cond_app07.pdf p.1 of 1 | — | Jun 12, 2026 |
| unconditional_waiver | waiver_uncond_app07.pdf p.1 of 1 | — | Jul 18, 2026 |