Coral Bay Surgical Center · C-CBS-2405-05 · period ending Jul 6, 2026 · PaidCompleted to date
$50,560,080
Stored materials
$0
Retainage withheld
$5,056,008
Retainage required
$5,056,008
Due this application
$4,161,186
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | $3,478,906 | $323,648 | $3,802,554 | — | 93% | $380,255 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | $2,540,046 | $254,295 | $2,794,341 | — | 78% | $279,434 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | $3,839,999 | $416,119 | $4,256,118 | — | 81% | $425,612 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | $5,872,599 | $693,531 | $6,566,130 | — | 75% | $656,613 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | $5,055,393 | $439,236 | $5,494,629 | — | 99% | $549,463 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | $2,236,440 | $208,059 | $2,444,499 | — | 93% | $244,450 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | $5,541,919 | $554,825 | $6,096,744 | — | 87% | $609,674 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | $2,986,666 | $323,648 | $3,310,314 | — | 81% | $331,031 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | $2,153,286 | $254,295 | $2,407,581 | — | 75% | $240,758 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | $3,192,880 | $277,412 | $3,470,292 | — | 99% | $347,029 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | $4,721,373 | $439,236 | $5,160,609 | — | 93% | $516,061 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | $3,463,700 | $346,766 | $3,810,465 | — | 87% | $381,047 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | $853,333 | $92,471 | $945,804 | — | 78% | $94,580 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $45,936,540 | $4,623,540 | $50,560,080 | $0 | 86% | $5,056,008 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app08.pdf p.1 of 5 | — | Jul 9, 2026 |
| conditional_waiver | waiver_cond_app08.pdf p.1 of 1 | — | Jul 12, 2026 |
| unconditional_waiver | waiver_uncond_app08.pdf p.1 of 1 | — | Aug 17, 2026 |