Coral Bay Surgical Center · C-CBS-2405-05 · period ending Aug 5, 2026 · CertifiedCompleted to date
$52,480,578
Stored materials
$0
Retainage withheld
$5,248,058
Retainage required
$5,248,058
Due this application
$1,728,448
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $4,102,000 | — | $4,102,000 | $3,802,554 | $149,313 | $3,951,867 | — | 96% | $395,187 |
| 2 | 02-200 | Sitework and excavation | $3,223,000 | $343,388 | $3,566,388 | $2,794,341 | $117,317 | $2,911,658 | — | 82% | $291,166 |
| 3 | 03-300 | Concrete, foundations | $5,274,000 | — | $5,274,000 | $4,256,118 | $191,974 | $4,448,092 | — | 84% | $444,809 |
| 4 | 03-330 | Concrete, superstructure | $8,790,000 | — | $8,790,000 | $6,566,130 | $319,956 | $6,886,086 | — | 78% | $688,609 |
| 5 | 05-100 | Structural steel | $5,567,000 | — | $5,567,000 | $5,494,629 | $72,371 | $5,567,000 | — | 100% | $556,700 |
| 6 | 07-500 | Roofing and waterproofing | $2,637,000 | — | $2,637,000 | $2,444,499 | $95,987 | $2,540,486 | — | 96% | $254,049 |
| 7 | 08-400 | Curtain wall and glazing | $7,032,000 | — | $7,032,000 | $6,096,744 | $255,965 | $6,352,709 | — | 90% | $635,271 |
| 8 | 09-250 | Drywall and framing | $4,102,000 | — | $4,102,000 | $3,310,314 | $149,313 | $3,459,627 | — | 84% | $345,963 |
| 9 | 09-650 | Flooring and finishes | $3,223,000 | — | $3,223,000 | $2,407,581 | $117,317 | $2,524,898 | — | 78% | $252,490 |
| 10 | 15-400 | Plumbing | $3,516,000 | — | $3,516,000 | $3,470,292 | $45,708 | $3,516,000 | — | 100% | $351,600 |
| 11 | 15-700 | HVAC | $5,567,000 | — | $5,567,000 | $5,160,609 | $202,639 | $5,363,248 | — | 96% | $536,325 |
| 12 | 16-100 | Electrical | $4,395,000 | — | $4,395,000 | $3,810,465 | $159,978 | $3,970,443 | — | 90% | $397,044 |
| 13 | 21-100 | Fire protection | $1,172,000 | $46,621 | $1,218,621 | $945,804 | $42,661 | $988,465 | — | 81% | $98,846 |
| Totals | $58,600,000 | $390,009 | $58,990,009 | $50,560,080 | $1,920,498 | $52,480,578 | $0 | 89% | $5,248,058 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app09.pdf p.1 of 8 | — | Aug 8, 2026 |
| conditional_waiver | waiver_cond_app09.pdf p.1 of 1 | — | Aug 11, 2026 |