Drawcheck
← Meridian Builders

Application 9

Coral Bay Surgical Center · C-CBS-2405-05 · period ending Aug 5, 2026 · Certified

Completed to date

$52,480,578

Stored materials

$0

Retainage withheld

$5,248,058

Retainage required

$5,248,058

Due this application

$1,728,448

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,102,000—$4,102,000$3,802,554$149,313$3,951,867—96%$395,187
202-200Sitework and excavation$3,223,000$343,388$3,566,388$2,794,341$117,317$2,911,658—82%$291,166
303-300Concrete, foundations$5,274,000—$5,274,000$4,256,118$191,974$4,448,092—84%$444,809
403-330Concrete, superstructure$8,790,000—$8,790,000$6,566,130$319,956$6,886,086—78%$688,609
505-100Structural steel$5,567,000—$5,567,000$5,494,629$72,371$5,567,000—100%$556,700
607-500Roofing and waterproofing$2,637,000—$2,637,000$2,444,499$95,987$2,540,486—96%$254,049
708-400Curtain wall and glazing$7,032,000—$7,032,000$6,096,744$255,965$6,352,709—90%$635,271
809-250Drywall and framing$4,102,000—$4,102,000$3,310,314$149,313$3,459,627—84%$345,963
909-650Flooring and finishes$3,223,000—$3,223,000$2,407,581$117,317$2,524,898—78%$252,490
1015-400Plumbing$3,516,000—$3,516,000$3,470,292$45,708$3,516,000—100%$351,600
1115-700HVAC$5,567,000—$5,567,000$5,160,609$202,639$5,363,248—96%$536,325
1216-100Electrical$4,395,000—$4,395,000$3,810,465$159,978$3,970,443—90%$397,044
1321-100Fire protection$1,172,000$46,621$1,218,621$945,804$42,661$988,465—81%$98,846
Totals$58,600,000$390,009$58,990,009$50,560,080$1,920,498$52,480,578$089%$5,248,058

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app09.pdf p.1 of 8—Aug 8, 2026
conditional_waiverwaiver_cond_app09.pdf p.1 of 1—Aug 11, 2026