Line 1 (General conditions) is billed to $4,348,120 against an adjusted scheduled value of $4,102,000
A schedule-of-values line cannot be worth more than its scheduled value plus the approved change orders against it. Anything above that is money claimed for scope that has not been priced or approved.
Remedy Reject the line back to its adjusted value and require the contractor to submit the difference as a change order.