Drawcheck
Vantage Construction Group

Application 1

Brickell Bay Tower · C-BRK-2201-01 · period ending May 2, 2025 · Paid

Completed to date

$2,022,191

Stored materials

$0

Retainage withheld

$202,219

Retainage required

$202,219

Due this application

$1,819,972

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$172,401$172,4012%$17,240
202-200Sitework and excavation$8,167,500$8,167,500$0$00%$0
303-300Concrete, foundations$13,365,000$13,365,000$0$00%$0
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$0$00%$0
505-100Structural steel$14,107,500$14,107,500$997,400$997,4007%$99,740
607-500Roofing and waterproofing$6,682,500$6,682,500$71,503$71,5031%$7,150
708-400Curtain wall and glazing$17,820,000$17,820,000$0$00%$0
809-250Drywall and framing$10,395,000$10,395,000$0$00%$0
909-650Flooring and finishes$8,167,500$8,167,500$0$00%$0
1015-400Plumbing$8,910,000$830,266$9,740,266$629,937$629,9376%$62,994
1115-700HVAC$14,107,500$662,148$14,769,648$150,950$150,9501%$15,095
1216-100Electrical$11,137,500$11,137,500$0$00%$0
1321-100Fire protection$2,970,000$2,970,000$0$00%$0
Totals$148,500,000$3,197,001$151,697,001$0$2,022,191$2,022,191$01%$202,219

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 9May 5, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1May 8, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1Jun 13, 2025