Application 10

Brickell Bay Tower · C-BRK-2201-01 · period ending Jan 27, 2026 · Paid

Completed to date

$125,101,375

Stored materials

$0

Retainage withheld

$12,510,137

Retainage required

$12,510,137

Due this application

$9,410,898

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000—$10,395,000$10,395,000$0$10,395,000—100%$1,039,500
202-200Sitework and excavation$8,167,500—$8,167,500$8,167,500$0$8,167,500—100%$816,750
303-300Concrete, foundations$13,365,000—$13,365,000$13,365,000$0$13,365,000—100%$1,336,500
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$13,217,985$1,998,068$15,216,053—63%$1,521,605
505-100Structural steel$14,107,500—$14,107,500$11,757,191$1,265,443$13,022,633—92%$1,302,263
607-500Roofing and waterproofing$6,682,500—$6,682,500$5,168,246$599,420$5,767,666—86%$576,767
708-400Curtain wall and glazing$17,820,000—$17,820,000$12,712,788$1,598,454$14,311,242—80%$1,431,124
809-250Drywall and framing$10,395,000—$10,395,000$6,792,093$932,432$7,724,525—74%$772,452
909-650Flooring and finishes$8,167,500—$8,167,500$4,846,595$732,625$5,579,219—68%$557,922
1015-400Plumbing$8,910,000$830,266$9,740,266$7,425,594$799,227$8,224,821—84%$822,482
1115-700HVAC$14,107,500$662,148$14,769,648$10,910,741$1,265,443$12,176,183—82%$1,217,618
1216-100Electrical$11,137,500—$11,137,500$7,945,493$999,034$8,944,526—80%$894,453
1321-100Fire protection$2,970,000—$2,970,000$1,940,598$266,409$2,207,007—74%$220,701
Totals$148,500,000$3,197,001$151,697,001$114,644,822$10,456,553$125,101,375$082%$12,510,137

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app10.pdf p.1 of 10—Jan 30, 2026
conditional_waiverwaiver_cond_app10.pdf p.1 of 1—Feb 2, 2026
unconditional_waiverwaiver_uncond_app10.pdf p.1 of 1—Mar 10, 2026