Vantage Construction Group

Application 11

Brickell Bay Tower · C-BRK-2201-01 · period ending Feb 26, 2026 · Paid

Completed to date

$131,617,778

Stored materials

$0

Retainage withheld

$13,161,778

Retainage required

$13,161,778

Due this application

$5,864,762

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$10,395,000$0$10,395,000100%$1,039,500
202-200Sitework and excavation$8,167,500$8,167,500$8,167,500$0$8,167,500100%$816,750
303-300Concrete, foundations$13,365,000$13,365,000$13,365,000$0$13,365,000100%$1,336,500
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$15,216,053$1,245,173$16,461,22569%$1,646,123
505-100Structural steel$14,107,500$14,107,500$13,022,633$788,609$13,811,24398%$1,381,124
607-500Roofing and waterproofing$6,682,500$6,682,500$5,767,666$373,552$6,141,21892%$614,122
708-400Curtain wall and glazing$17,820,000$17,820,000$14,311,242$996,138$15,307,38086%$1,530,738
809-250Drywall and framing$10,395,000$10,395,000$7,724,525$581,081$8,305,60580%$830,561
909-650Flooring and finishes$8,167,500$8,167,500$5,579,219$456,563$6,035,78374%$603,578
1015-400Plumbing$8,910,000$830,266$9,740,266$8,224,821$498,069$8,722,89090%$872,289
1115-700HVAC$14,107,500$662,148$14,769,648$12,176,183$788,609$12,964,79388%$1,296,479
1216-100Electrical$11,137,500$11,137,500$8,944,526$622,586$9,567,11386%$956,711
1321-100Fire protection$2,970,000$2,970,000$2,207,007$166,023$2,373,03080%$237,303
Totals$148,500,000$3,197,001$151,697,001$125,101,375$6,516,403$131,617,778$087%$13,161,778

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app11.pdf p.1 of 13Mar 1, 2026
conditional_waiverwaiver_cond_app11.pdf p.1 of 1Mar 4, 2026
unconditional_waiverwaiver_uncond_app11.pdf p.1 of 1Apr 9, 2026