Drawcheck
Vantage Construction Group

Application 13

Brickell Bay Tower · C-BRK-2201-01 · period ending Apr 27, 2026 · Certified

Completed to date

$136,806,962

Stored materials

$0

Retainage withheld

$8,482,032

Retainage required

$13,680,696

Due this application

$1,570,807

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$10,395,000$0$10,395,000100%$644,490
202-200Sitework and excavation$8,167,500$8,167,500$8,167,500$0$8,167,500100%$506,385
303-300Concrete, foundations$13,365,000$13,365,000$13,365,000$0$13,365,000100%$828,630
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$17,182,935$398,723$17,581,65873%$1,090,063
505-100Structural steel$14,107,500$14,107,500$14,107,500$0$14,107,500100%$874,665
607-500Roofing and waterproofing$6,682,500$6,682,500$6,357,731$119,617$6,477,34797%$401,596
708-400Curtain wall and glazing$17,820,000$17,820,000$15,884,748$318,978$16,203,72691%$1,004,631
809-250Drywall and framing$10,395,000$10,395,000$8,642,403$186,071$8,828,47485%$547,365
909-650Flooring and finishes$8,167,500$8,167,500$6,300,410$146,198$6,446,60879%$399,690
1015-400Plumbing$8,910,000$830,266$9,740,266$8,910,000$0$8,910,00091%$552,420
1115-700HVAC$14,107,500$662,148$14,769,648$13,421,876$252,524$13,674,40093%$847,813
1216-100Electrical$11,137,500$11,137,500$9,927,968$199,361$10,127,32991%$627,894
1321-100Fire protection$2,970,000$2,970,000$2,469,258$53,163$2,522,42185%$156,390
Totals$148,500,000$3,197,001$151,697,001$135,132,327$1,674,635$136,806,962$090%$8,482,032

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app13.pdf p.1 of 13Apr 30, 2026
conditional_waiverwaiver_cond_app13.pdf p.1 of 1May 3, 2026