Brickell Bay Tower · C-BRK-2201-01 · period ending May 27, 2026 · Submitted

Completed to date

$137,714,445

Stored materials

$0

Retainage withheld

$8,538,296

Retainage required

$13,771,445

Due this application

$851,220

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$10,395,000$0$10,395,000100%$644,490
202-200Sitework and excavation$8,167,500$8,167,500$8,167,500$0$8,167,500100%$506,385
303-300Concrete, foundations$13,365,000$13,365,000$13,365,000$0$13,365,000100%$828,630
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$17,581,658$216,068$17,797,72574%$1,103,459
505-100Structural steel$14,107,500$14,107,500$14,107,500$0$14,107,500100%$874,665
607-500Roofing and waterproofing$6,682,500$6,682,500$6,477,347$64,820$6,542,16898%$405,614
708-400Curtain wall and glazing$17,820,000$17,820,000$16,203,726$172,854$16,376,58092%$1,015,348
809-250Drywall and framing$10,395,000$10,395,000$8,828,474$100,832$8,929,30586%$553,617
909-650Flooring and finishes$8,167,500$8,167,500$6,446,608$79,225$6,525,83380%$404,602
1015-400Plumbing$8,910,000$830,266$9,740,266$8,910,000$0$8,910,00091%$552,420
1115-700HVAC$14,107,500$662,148$14,769,648$13,674,400$136,843$13,811,24394%$856,297
1216-100Electrical$11,137,500$11,137,500$10,127,329$108,034$10,235,36392%$634,592
1321-100Fire protection$2,970,000$2,970,000$2,522,421$28,809$2,551,23086%$158,176
Totals$148,500,000$3,197,001$151,697,001$136,806,962$907,484$137,714,445$091%$8,538,296

Exceptions on this application

CriticalBILLING-AHEAD-OF-PROGRESSBilling materially ahead of observed progress$21,298,259

Application 14 bills 90.8 percent of the adjusted contract against an observed 76.7 percent complete on Aug 27 2026

Front loading moves the contractor's risk onto the owner. If the contractor leaves the job, the remaining money will not buy the remaining work, and that gap is only visible before it is paid.

Remedy Reduce the certification to observed progress and require a revised schedule of values for the remaining lines.

claimed 90.8%supported 76.7%
HighRETAINAGE-SHORTRetainage withheld below the contract percentage$5,233,149

Retainage withheld on application 14 is $8,538,296 against $13,771,445 required at 10.0 percent

Retainage is the owner's only remaining leverage at closeout. Under-withholding gives it away quietly, one draw at a time, and it is almost never noticed until the punch list stalls.

Remedy Correct the withholding on this application and reconcile every prior application in the same certification.

claimed $8,538,296supported $13,771,445

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app14.pdf p.1 of 4May 30, 2026
conditional_waiverwaiver_cond_app14.pdf p.1 of 1Jun 2, 2026