Drawcheck
Cordova Glass Systems

Application 1

Brickell Bay Tower · C-BRK-2201-02 · period ending May 2, 2025 · Paid

Completed to date

$252,688

Stored materials

$0

Retainage withheld

$25,269

Retainage required

$25,269

Due this application

$227,420

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$32,368$32,3681%$3,237
205-100Structural steel$4,789,583$4,789,583$0$00%$0
302-200Sitework and excavation$2,772,917$2,772,917$0$00%$0
421-100Fire protection$1,008,333$44,898$1,053,232$0$00%$0
509-650Flooring and finishes$2,772,917$243,502$3,016,418$196,045$196,0457%$19,605
607-500Roofing and waterproofing$2,268,750$2,268,750$24,276$24,2761%$2,428
703-330Concrete, superstructure$7,562,500$7,562,500$0$00%$0
Totals$24,200,000$428,027$24,628,027$0$252,688$252,688$01%$25,269

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 12May 5, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1May 8, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1Jun 13, 2025