Drawcheck
Cordova Glass Systems

Application 2

Brickell Bay Tower · C-BRK-2201-02 · period ending Jun 1, 2025 · Paid

Completed to date

$397,082

Stored materials

$110,917

Retainage withheld

$50,800

Retainage required

$50,800

Due this application

$229,779

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$32,368$54,148$86,5153%$8,652
205-100Structural steel$4,789,583$4,789,583$0$0$00%$0
302-200Sitework and excavation$2,772,917$2,772,917$0$0$00%$0
421-100Fire protection$1,008,333$44,898$1,053,232$0$0$00%$0
509-650Flooring and finishes$2,772,917$243,502$3,016,418$196,045$49,635$245,680$110,9178%$35,660
607-500Roofing and waterproofing$2,268,750$2,268,750$24,276$40,611$64,8863%$6,489
703-330Concrete, superstructure$7,562,500$7,562,500$0$0$00%$0
Totals$24,200,000$428,027$24,628,027$252,688$144,393$397,082$110,9172%$50,800

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app02.pdf p.1 of 8Jun 4, 2025
conditional_waiverwaiver_cond_app02.pdf p.1 of 1Jun 7, 2025
supplier_invoiceinvoice_app02.pdf p.1 of 1$90,750Jun 5, 2025
unconditional_waiverwaiver_uncond_app02.pdf p.1 of 1Jul 13, 2025