Cordova Glass Systems

Application 3

Brickell Bay Tower · C-BRK-2201-02 · period ending Jul 1, 2025 · Paid

Completed to date

$670,794

Stored materials

$110,917

Retainage withheld

$78,171

Retainage required

$78,171

Due this application

$246,341

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$86,515$98,010$184,5256%$18,453
205-100Structural steel$4,789,583$4,789,583$0$4,790$4,7900%$479
302-200Sitework and excavation$2,772,917$2,772,917$0$0$00%$0
421-100Fire protection$1,008,333$44,898$1,053,232$0$0$00%$0
509-650Flooring and finishes$2,772,917$243,502$3,016,418$245,680$89,843$335,523$110,91711%$44,644
607-500Roofing and waterproofing$2,268,750$2,268,750$64,886$73,508$138,3946%$13,839
703-330Concrete, superstructure$7,562,500$7,562,500$0$7,563$7,5630%$756
Totals$24,200,000$428,027$24,628,027$397,082$273,712$670,794$110,9173%$78,171

Exceptions on this application

HighSTORED-NO-INVOICEStored materials claimed without supplier documentation$110,917

$110,917 of stored materials claimed on line 5 with no supplier invoice or bill of sale in the application

Stored materials are paid for before they are installed, so the only protection is proof the material exists, is paid for, and is titled to the project.

Remedy Require the supplier invoice, a bill of sale, and evidence of insured off-site storage before releasing the stored materials amount.

claimed $110,917supported supporting invoice requiredcontinuation line 5 (09-650)

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 10Jul 4, 2025
conditional_waiverwaiver_cond_app03.pdf p.1 of 1Jul 7, 2025
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1Aug 12, 2025