Drawcheck
Cordova Glass Systems

Application 4

Brickell Bay Tower · C-BRK-2201-02 · period ending Jul 31, 2025 · Paid

Completed to date

$1,812,202

Stored materials

$0

Retainage withheld

$181,220

Retainage required

$181,220

Due this application

$927,442

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$184,525$169,098$353,62311%$35,362
205-100Structural steel$4,789,583$4,789,583$4,790$267,738$272,5276%$27,253
302-200Sitework and excavation$2,772,917$2,772,917$0$0$00%$0
421-100Fire protection$1,008,333$44,898$1,053,232$0$0$00%$0
509-650Flooring and finishes$2,772,917$243,502$3,016,418$335,523$155,006$490,52916%$49,053
607-500Roofing and waterproofing$2,268,750$2,268,750$138,394$126,823$265,21712%$26,522
703-330Concrete, superstructure$7,562,500$7,562,500$7,563$422,744$430,3066%$43,031
Totals$24,200,000$428,027$24,628,027$670,794$1,141,408$1,812,202$07%$181,220

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 12Aug 3, 2025
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Aug 6, 2025
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Sep 11, 2025