Drawcheck
Cordova Glass Systems

Application 5

Brickell Bay Tower · C-BRK-2201-02 · period ending Aug 30, 2025 · Paid

Completed to date

$3,910,720

Stored materials

$0

Retainage withheld

$391,072

Retainage required

$391,072

Due this application

$1,888,666

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$353,623$271,343$624,96520%$62,497
205-100Structural steel$4,789,583$4,789,583$272,527$429,626$702,15315%$70,215
302-200Sitework and excavation$2,772,917$2,772,917$0$240,135$240,1359%$24,013
421-100Fire protection$1,008,333$44,898$1,053,232$0$26,822$26,8223%$2,682
509-650Flooring and finishes$2,772,917$243,502$3,016,418$490,529$248,731$739,26025%$73,926
607-500Roofing and waterproofing$2,268,750$2,268,750$265,217$203,507$468,72421%$46,872
703-330Concrete, superstructure$7,562,500$7,562,500$430,306$678,356$1,108,66315%$110,866
Totals$24,200,000$428,027$24,628,027$1,812,202$2,098,518$3,910,720$016%$391,072

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 7Sep 2, 2025
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Sep 5, 2025
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1Oct 11, 2025