Drawcheck
Cordova Glass Systems

Application 6

Brickell Bay Tower · C-BRK-2201-02 · period ending Sep 29, 2025 · Paid

Completed to date

$7,008,320

Stored materials

$0

Retainage withheld

$700,832

Retainage required

$700,832

Due this application

$2,787,840

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$624,965$387,200$1,012,16532%$101,217
205-100Structural steel$4,789,583$4,789,583$702,153$613,067$1,315,22027%$131,522
302-200Sitework and excavation$2,772,917$2,772,917$240,135$354,933$595,06821%$59,507
421-100Fire protection$1,008,333$44,898$1,053,232$26,822$129,067$155,88815%$15,589
509-650Flooring and finishes$2,772,917$243,502$3,016,418$739,260$354,933$1,094,19336%$109,419
607-500Roofing and waterproofing$2,268,750$2,268,750$468,724$290,400$759,12433%$75,912
703-330Concrete, superstructure$7,562,500$7,562,500$1,108,663$968,000$2,076,66327%$207,666
Totals$24,200,000$428,027$24,628,027$3,910,720$3,097,600$7,008,320$028%$700,832

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app06.pdf p.1 of 12Oct 2, 2025
conditional_waiverwaiver_cond_app06.pdf p.1 of 1Oct 5, 2025
unconditional_waiverwaiver_uncond_app06.pdf p.1 of 1Nov 10, 2025