Drawcheck
Cordova Glass Systems

Application 7

Brickell Bay Tower · C-BRK-2201-02 · period ending Oct 29, 2025 · Paid

Completed to date

$10,769,000

Stored materials

$0

Retainage withheld

$1,076,900

Retainage required

$1,076,900

Due this application

$3,384,612

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$1,012,165$470,085$1,482,25047%$148,225
205-100Structural steel$4,789,583$4,789,583$1,315,220$744,301$2,059,52143%$205,952
302-200Sitework and excavation$2,772,917$2,772,917$595,068$430,911$1,025,97937%$102,598
421-100Fire protection$1,008,333$44,898$1,053,232$155,888$156,695$312,58330%$31,258
509-650Flooring and finishes$2,772,917$243,502$3,016,418$1,094,193$430,911$1,525,10451%$152,510
607-500Roofing and waterproofing$2,268,750$2,268,750$759,124$352,564$1,111,68849%$111,169
703-330Concrete, superstructure$7,562,500$7,562,500$2,076,663$1,175,213$3,251,87543%$325,188
Totals$24,200,000$428,027$24,628,027$7,008,320$3,760,680$10,769,000$044%$1,076,900

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app07.pdf p.1 of 5Nov 1, 2025
conditional_waiverwaiver_cond_app07.pdf p.1 of 1Nov 4, 2025
unconditional_waiverwaiver_uncond_app07.pdf p.1 of 1Dec 10, 2025