Drawcheck
Cordova Glass Systems

Application 8

Brickell Bay Tower · C-BRK-2201-02 · period ending Nov 28, 2025 · Paid

Completed to date

$14,529,680

Stored materials

$0

Retainage withheld

$1,452,968

Retainage required

$1,452,968

Due this application

$3,384,612

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$1,482,250$470,085$1,952,33562%$195,234
205-100Structural steel$4,789,583$4,789,583$2,059,521$744,301$2,803,82259%$280,382
302-200Sitework and excavation$2,772,917$2,772,917$1,025,979$430,911$1,456,89053%$145,689
421-100Fire protection$1,008,333$44,898$1,053,232$312,583$156,695$469,27845%$46,928
509-650Flooring and finishes$2,772,917$243,502$3,016,418$1,525,104$430,911$1,956,01565%$195,602
607-500Roofing and waterproofing$2,268,750$2,268,750$1,111,688$352,564$1,464,25165%$146,425
703-330Concrete, superstructure$7,562,500$7,562,500$3,251,875$1,175,213$4,427,08859%$442,709
Totals$24,200,000$428,027$24,628,027$10,769,000$3,760,680$14,529,680$059%$1,452,968

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app08.pdf p.1 of 4Dec 1, 2025
conditional_waiverwaiver_cond_app08.pdf p.1 of 1Dec 4, 2025
unconditional_waiverwaiver_uncond_app08.pdf p.1 of 1Jan 9, 2026