Drawcheck
Cordova Glass Systems

Application 9

Brickell Bay Tower · C-BRK-2201-02 · period ending Dec 28, 2025 · Paid

Completed to date

$17,627,280

Stored materials

$0

Retainage withheld

$1,762,728

Retainage required

$1,762,728

Due this application

$2,787,840

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$1,952,335$387,200$2,339,53574%$233,954
205-100Structural steel$4,789,583$4,789,583$2,803,822$613,067$3,416,88971%$341,689
302-200Sitework and excavation$2,772,917$2,772,917$1,456,890$354,933$1,811,82465%$181,182
421-100Fire protection$1,008,333$44,898$1,053,232$469,278$129,067$598,34557%$59,835
509-650Flooring and finishes$2,772,917$243,502$3,016,418$1,956,015$354,933$2,310,94977%$231,095
607-500Roofing and waterproofing$2,268,750$2,268,750$1,464,251$290,400$1,754,65177%$175,465
703-330Concrete, superstructure$7,562,500$7,562,500$4,427,088$968,000$5,395,08871%$539,509
Totals$24,200,000$428,027$24,628,027$14,529,680$3,097,600$17,627,280$072%$1,762,728

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app09.pdf p.1 of 7Dec 31, 2025
conditional_waiverwaiver_cond_app09.pdf p.1 of 1Jan 3, 2026
unconditional_waiverwaiver_uncond_app09.pdf p.1 of 1Feb 8, 2026