Drawcheck
Cordova Glass Systems

Application 10

Brickell Bay Tower · C-BRK-2201-02 · period ending Jan 27, 2026 · Paid

Completed to date

$19,798,020

Stored materials

$0

Retainage withheld

$1,979,802

Retainage required

$1,979,802

Due this application

$1,953,666

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$2,339,535$271,343$2,610,87883%$261,088
205-100Structural steel$4,789,583$4,789,583$3,416,889$429,626$3,846,51480%$384,651
302-200Sitework and excavation$2,772,917$2,772,917$1,811,824$248,731$2,060,55474%$206,055
421-100Fire protection$1,008,333$44,898$1,053,232$598,345$90,448$688,79365%$68,879
509-650Flooring and finishes$2,772,917$243,502$3,016,418$2,310,949$248,731$2,559,67985%$255,968
607-500Roofing and waterproofing$2,268,750$2,268,750$1,754,651$203,507$1,958,15886%$195,816
703-330Concrete, superstructure$7,562,500$7,562,500$5,395,088$678,356$6,073,44480%$607,344
Totals$24,200,000$428,027$24,628,027$17,627,280$2,170,740$19,798,020$080%$1,979,802

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app10.pdf p.1 of 10Jan 30, 2026
conditional_waiverwaiver_cond_app10.pdf p.1 of 1Feb 2, 2026
unconditional_waiverwaiver_uncond_app10.pdf p.1 of 1Mar 10, 2026