Drawcheck
Cordova Glass Systems

Application 11

Brickell Bay Tower · C-BRK-2201-02 · period ending Feb 26, 2026 · Paid

Completed to date

$21,150,800

Stored materials

$0

Retainage withheld

$2,115,080

Retainage required

$2,115,080

Due this application

$1,217,502

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$2,610,878$169,098$2,779,97588%$277,998
205-100Structural steel$4,789,583$4,789,583$3,846,514$267,738$4,114,25286%$411,425
302-200Sitework and excavation$2,772,917$2,772,917$2,060,554$155,006$2,215,56080%$221,556
421-100Fire protection$1,008,333$44,898$1,053,232$688,793$56,366$745,15871%$74,516
509-650Flooring and finishes$2,772,917$243,502$3,016,418$2,559,679$155,006$2,714,68590%$271,469
607-500Roofing and waterproofing$2,268,750$2,268,750$1,958,158$126,823$2,084,98192%$208,498
703-330Concrete, superstructure$7,562,500$7,562,500$6,073,444$422,744$6,496,18886%$649,619
Totals$24,200,000$428,027$24,628,027$19,798,020$1,352,780$21,150,800$086%$2,115,080

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app11.pdf p.1 of 12Mar 1, 2026
conditional_waiverwaiver_cond_app11.pdf p.1 of 1Mar 4, 2026
unconditional_waiverwaiver_uncond_app11.pdf p.1 of 1Apr 9, 2026