Brickell Bay Tower · C-BRK-2201-02 · period ending Mar 28, 2026 · Paid

Completed to date

$21,903,269

Stored materials

$0

Retainage withheld

$2,190,327

Retainage required

$2,190,327

Due this application

$677,222

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$2,779,975$98,010$2,877,98591%$287,799
205-100Structural steel$4,789,583$4,789,583$4,114,252$155,183$4,269,43589%$426,943
302-200Sitework and excavation$2,772,917$2,772,917$2,215,560$89,843$2,305,40383%$230,540
421-100Fire protection$1,008,333$44,898$1,053,232$745,158$32,670$777,82874%$77,783
509-650Flooring and finishes$2,772,917$243,502$3,016,418$2,714,685$58,231$2,772,91792%$277,292
607-500Roofing and waterproofing$2,268,750$2,268,750$2,084,981$73,508$2,158,48995%$215,849
703-330Concrete, superstructure$7,562,500$7,562,500$6,496,188$245,025$6,741,21389%$674,121
Totals$24,200,000$428,027$24,628,027$21,150,800$752,469$21,903,269$089%$2,190,327

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app12.pdf p.1 of 9Mar 31, 2026
conditional_waiverwaiver_cond_app12.pdf p.1 of 1Apr 3, 2026
unconditional_waiverwaiver_uncond_app12.pdf p.1 of 1May 9, 2026