← Cordova Glass Systems
Application 13
Brickell Bay Tower · C-BRK-2201-02 · period ending Apr 27, 2026 · CertifiedCompleted to date
$22,286,814
Stored materials
$0
Retainage withheld
$2,228,681
Retainage required
$2,228,681
Due this application
$345,190
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 15-400 | Plumbing | $3,025,000 | $139,627 | $3,164,627 | $2,877,985 | $54,148 | $2,932,133 | — | 93% | $293,213 |
| 2 | 05-100 | Structural steel | $4,789,583 | — | $4,789,583 | $4,269,435 | $85,734 | $4,355,168 | — | 91% | $435,517 |
| 3 | 02-200 | Sitework and excavation | $2,772,917 | — | $2,772,917 | $2,305,403 | $49,635 | $2,355,038 | — | 85% | $235,504 |
| 4 | 21-100 | Fire protection | $1,008,333 | $44,898 | $1,053,232 | $777,828 | $18,049 | $795,878 | — | 76% | $79,588 |
| 5 | 09-650 | Flooring and finishes | $2,772,917 | $243,502 | $3,016,418 | $2,772,917 | $0 | $2,772,917 | — | 92% | $277,292 |
| 6 | 07-500 | Roofing and waterproofing | $2,268,750 | — | $2,268,750 | $2,158,489 | $40,611 | $2,199,099 | — | 97% | $219,910 |
| 7 | 03-330 | Concrete, superstructure | $7,562,500 | — | $7,562,500 | $6,741,213 | $135,369 | $6,876,581 | — | 91% | $687,658 |
| Totals | $24,200,000 | $428,027 | $24,628,027 | $21,903,269 | $383,545 | $22,286,814 | $0 | 90% | $2,228,681 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app13.pdf p.1 of 9 | — | Apr 30, 2026 |
| conditional_waiver | waiver_cond_app13.pdf p.1 of 1 | — | May 3, 2026 |