Drawcheck
Cordova Glass Systems

Application 13

Brickell Bay Tower · C-BRK-2201-02 · period ending Apr 27, 2026 · Certified

Completed to date

$22,286,814

Stored materials

$0

Retainage withheld

$2,228,681

Retainage required

$2,228,681

Due this application

$345,190

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
115-400Plumbing$3,025,000$139,627$3,164,627$2,877,985$54,148$2,932,13393%$293,213
205-100Structural steel$4,789,583$4,789,583$4,269,435$85,734$4,355,16891%$435,517
302-200Sitework and excavation$2,772,917$2,772,917$2,305,403$49,635$2,355,03885%$235,504
421-100Fire protection$1,008,333$44,898$1,053,232$777,828$18,049$795,87876%$79,588
509-650Flooring and finishes$2,772,917$243,502$3,016,418$2,772,917$0$2,772,91792%$277,292
607-500Roofing and waterproofing$2,268,750$2,268,750$2,158,489$40,611$2,199,09997%$219,910
703-330Concrete, superstructure$7,562,500$7,562,500$6,741,213$135,369$6,876,58191%$687,658
Totals$24,200,000$428,027$24,628,027$21,903,269$383,545$22,286,814$090%$2,228,681

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app13.pdf p.1 of 9Apr 30, 2026
conditional_waiverwaiver_cond_app13.pdf p.1 of 1May 3, 2026