Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Sep 19, 2025 · Paid

Completed to date

$1,002,813

Stored materials

$0

Retainage withheld

$100,281

Retainage required

$100,281

Due this application

$902,532

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$64,974$64,9741%$6,497
202-200Sitework and excavation$3,927,000$338,921$4,265,921$0$00%$0
303-300Concrete, foundations$6,426,000$524,940$6,950,940$0$00%$0
403-330Concrete, superstructure$10,710,000$10,710,000$0$00%$0
505-100Structural steel$6,783,000$314,616$7,097,616$495,159$495,1597%$49,516
607-500Roofing and waterproofing$3,213,000$3,213,000$41,769$41,7691%$4,177
708-400Curtain wall and glazing$8,568,000$8,568,000$0$00%$0
809-250Drywall and framing$4,998,000$4,998,000$0$00%$0
909-650Flooring and finishes$3,927,000$3,927,000$0$00%$0
1015-400Plumbing$4,284,000$4,284,000$312,732$312,7327%$31,273
1115-700HVAC$6,783,000$6,783,000$88,179$88,1791%$8,818
1216-100Electrical$5,355,000$5,355,000$0$00%$0
1321-100Fire protection$1,428,000$1,428,000$0$00%$0
Totals$71,400,000$1,178,477$72,578,477$0$1,002,813$1,002,813$01%$100,281

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 12Sep 22, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1Sep 25, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1Oct 31, 2025