Application 10 was paid on Jul 26 2026 and no unconditional lien waiver has been received for it
claimed no waiver on filesupported unconditional waiver required
WYN-2304 · Wynwood Yards Mixed Use
C-WYN-2304-03 · original $71,400,000 · retainage 10% · owner Wynwood Yards Holdings LP · lender Synovus
Adjusted value
$72,578,477
Billed to date
$64,885,107 (89%)
Observed complete
89%
Amount at issue
$3,052,157
progress observed Aug 27, 2026 by Owner representative site walk · source site_observation_wyn-2304.pdf p.4
| App | Period ending | Status | Completed to date | This period | Retainage held | Retainage required | Due | % billed |
|---|---|---|---|---|---|---|---|---|
| 1 | Sep 19, 2025 | Paid | $1,002,813 | $1,002,813 | $100,281 | $100,281 | $902,532 | 1% |
| 2 | Oct 19, 2025 | Paid | $1,638,701 | $635,888 | $191,002 | $191,002 | $816,488 | 2% |
| 3 | Nov 18, 2025 | Paid | $3,338,628 | $1,699,927 | $360,995 | $360,995 | $1,529,934 | 5% |
| 4 | Dec 18, 2025 | Paid | $7,836,721 | $4,498,093 | $783,672 | $783,672 | $3,804,096 | 11% |
| 5 | Jan 17, 2026 | Paid | $17,607,240 | $9,770,519 | $1,760,724 | $1,760,724 | $8,793,467 | 24% |
| 6 | Feb 16, 2026 | Paid | $30,402,120 | $12,794,880 | $3,040,212 | $3,040,212 | $11,515,392 | 42% |
| 7 | Mar 18, 2026 | Paid | $43,197,000 | $12,794,880 | $4,319,700 | $4,319,700 | $11,515,392 | 60% |
| 8 | Apr 17, 2026 | Paid | $53,078,760 | $9,881,760 | $5,307,876 | $5,307,876 | $8,893,584 | 73% |
| 9 | May 17, 2026 | Paid | $59,297,700 | $6,218,940 | $5,929,770 | $5,929,770 | $5,597,046 | 82% |
| 10 | Jun 16, 2026 | Paid | $62,688,986 | $3,391,286 | $6,268,899 | $6,268,899 | $3,052,157 | 86% |
| 11 | Jul 16, 2026 | Certified | $64,161,111 | $1,472,125 | $6,416,111 | $6,416,111 | $1,324,913 | 88% |
| 12 | Aug 15, 2026 | Submitted | $64,885,107 | $723,996 | $6,488,511 | $6,488,511 | $651,596 | 89% |
| Number | Description | Applies to | Status | Approved | Amount |
|---|---|---|---|---|---|
| CO-001 | Owner-directed revision, concrete, foundations | line 3 — Concrete, foundations | approved | Nov 10, 2025 | $524,940 |
| CO-002 | Owner-directed revision, sitework and excavation | line 2 — Sitework and excavation | approved | Dec 10, 2025 | $338,921 |
| CO-003 | Owner-directed revision, structural steel | line 5 — Structural steel | approved | Jan 9, 2026 | $314,616 |
Application 10 was paid on Jul 26 2026 and no unconditional lien waiver has been received for it