Drawcheck
Vantage Construction Group

Application 3

Brickell Bay Tower · C-BRK-2201-01 · period ending Jul 1, 2025 · Paid

Completed to date

$5,077,772

Stored materials

$564,300

Retainage withheld

$564,207

Retainage required

$564,207

Due this application

$1,784,715

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$460,810$522,037$982,8479%$98,285
202-200Sitework and excavation$8,167,500$8,167,500$0$12,660$12,6600%$1,266
303-300Concrete, foundations$13,365,000$13,365,000$0$0$00%$0
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$0$0$00%$0
505-100Structural steel$14,107,500$14,107,500$1,249,925$457,083$1,707,008$564,30012%$227,131
607-500Roofing and waterproofing$6,682,500$6,682,500$191,120$216,513$407,6336%$40,763
708-400Curtain wall and glazing$17,820,000$17,820,000$0$17,820$17,8200%$1,782
809-250Drywall and framing$10,395,000$10,395,000$0$0$00%$0
909-650Flooring and finishes$8,167,500$8,167,500$0$0$00%$0
1015-400Plumbing$8,910,000$830,266$9,740,266$789,426$288,684$1,078,11011%$107,811
1115-700HVAC$14,107,500$662,148$14,769,648$403,475$457,083$860,5586%$86,056
1216-100Electrical$11,137,500$11,137,500$0$11,138$11,1380%$1,114
1321-100Fire protection$2,970,000$2,970,000$0$0$00%$0
Totals$148,500,000$3,197,001$151,697,001$3,094,755$1,983,017$5,077,772$564,3003%$564,207

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 5Jul 4, 2025
conditional_waiverwaiver_cond_app03.pdf p.1 of 1Jul 7, 2025
supplier_invoiceinvoice_app03.pdf p.1 of 1$311,850Jul 5, 2025
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1Aug 12, 2025