Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Oct 19, 2025 · Paid

Completed to date

$1,638,701

Stored materials

$271,320

Retainage withheld

$191,002

Retainage required

$191,002

Due this application

$816,488

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$64,974$121,951$186,9254%$18,693
202-200Sitework and excavation$3,927,000$338,921$4,265,921$0$0$00%$0
303-300Concrete, foundations$6,426,000$524,940$6,950,940$0$0$00%$0
403-330Concrete, superstructure$10,710,000$10,710,000$0$0$00%$0
505-100Structural steel$6,783,000$314,616$7,097,616$495,159$165,505$660,664$271,3209%$93,198
607-500Roofing and waterproofing$3,213,000$3,213,000$41,769$78,397$120,1664%$12,017
708-400Curtain wall and glazing$8,568,000$8,568,000$0$0$00%$0
809-250Drywall and framing$4,998,000$4,998,000$0$0$00%$0
909-650Flooring and finishes$3,927,000$3,927,000$0$0$00%$0
1015-400Plumbing$4,284,000$4,284,000$312,732$104,530$417,26210%$41,726
1115-700HVAC$6,783,000$6,783,000$88,179$165,505$253,6844%$25,368
1216-100Electrical$5,355,000$5,355,000$0$0$00%$0
1321-100Fire protection$1,428,000$1,428,000$0$0$00%$0
Totals$71,400,000$1,178,477$72,578,477$1,002,813$635,888$1,638,701$271,3202%$191,002

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app02.pdf p.1 of 11Oct 22, 2025
conditional_waiverwaiver_cond_app02.pdf p.1 of 1Oct 25, 2025
supplier_invoiceinvoice_app02.pdf p.1 of 2$149,940Oct 23, 2025
unconditional_waiverwaiver_uncond_app02.pdf p.1 of 1Nov 30, 2025