Application 3

Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Nov 18, 2025 · Paid

Completed to date

$3,338,628

Stored materials

$271,320

Retainage withheld

$360,995

Retainage required

$360,995

Due this application

$1,529,934

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000—$4,998,000$186,925$239,404$426,329—9%$42,633
202-200Sitework and excavation$3,927,000$338,921$4,265,921$0$99,353$99,353—2%$9,935
303-300Concrete, foundations$6,426,000$524,940$6,950,940$0$0$0—0%$0
403-330Concrete, superstructure$10,710,000—$10,710,000$0$0$0—0%$0
505-100Structural steel$6,783,000$314,616$7,097,616$660,664$324,906$985,570$271,32014%$125,689
607-500Roofing and waterproofing$3,213,000—$3,213,000$120,166$153,903$274,069—9%$27,407
708-400Curtain wall and glazing$8,568,000—$8,568,000$0$216,770$216,770—3%$21,677
809-250Drywall and framing$4,998,000—$4,998,000$0$0$0—0%$0
909-650Flooring and finishes$3,927,000—$3,927,000$0$0$0—0%$0
1015-400Plumbing$4,284,000—$4,284,000$417,262$205,204$622,465—15%$62,247
1115-700HVAC$6,783,000—$6,783,000$253,684$324,906$578,590—9%$57,859
1216-100Electrical$5,355,000—$5,355,000$0$135,482$135,482—3%$13,548
1321-100Fire protection$1,428,000—$1,428,000$0$0$0—0%$0
Totals$71,400,000$1,178,477$72,578,477$1,638,701$1,699,927$3,338,628$271,3205%$360,995

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 11—Nov 21, 2025
conditional_waiverwaiver_cond_app03.pdf p.1 of 1—Nov 24, 2025
supplier_invoiceinvoice_app03.pdf p.1 of 1$149,940Nov 22, 2025
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1—Dec 30, 2025