Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Dec 18, 2025 · Paid

Completed to date

$7,836,721

Stored materials

$0

Retainage withheld

$783,672

Retainage required

$783,672

Due this application

$3,804,096

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$426,329$435,326$861,65517%$86,166
202-200Sitework and excavation$3,927,000$338,921$4,265,921$99,353$342,042$441,39510%$44,139
303-300Concrete, foundations$6,426,000$524,940$6,950,940$0$336,722$336,7225%$33,672
403-330Concrete, superstructure$10,710,000$10,710,000$0$0$00%$0
505-100Structural steel$6,783,000$314,616$7,097,616$985,570$590,799$1,576,36922%$157,637
607-500Roofing and waterproofing$3,213,000$3,213,000$274,069$279,852$553,92117%$55,392
708-400Curtain wall and glazing$8,568,000$8,568,000$216,770$746,273$963,04311%$96,304
809-250Drywall and framing$4,998,000$4,998,000$0$261,895$261,8955%$26,190
909-650Flooring and finishes$3,927,000$3,927,000$0$0$00%$0
1015-400Plumbing$4,284,000$4,284,000$622,465$373,136$995,60223%$99,560
1115-700HVAC$6,783,000$6,783,000$578,590$590,799$1,169,38917%$116,939
1216-100Electrical$5,355,000$5,355,000$135,482$466,421$601,90211%$60,190
1321-100Fire protection$1,428,000$1,428,000$0$74,827$74,8275%$7,483
Totals$71,400,000$1,178,477$72,578,477$3,338,628$4,498,093$7,836,721$011%$783,672

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 11Dec 21, 2025
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Dec 24, 2025
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Jan 29, 2026