Drawcheck
Meridian Builders

Application 5

Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Jan 17, 2026 · Paid

Completed to date

$17,607,240

Stored materials

$0

Retainage withheld

$1,760,724

Retainage required

$1,760,724

Due this application

$8,793,467

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$861,655$691,723$1,553,37831%$155,338
202-200Sitework and excavation$3,927,000$338,921$4,265,921$441,395$543,497$984,89223%$98,489
303-300Concrete, foundations$6,426,000$524,940$6,950,940$336,722$889,358$1,226,08118%$122,608
403-330Concrete, superstructure$10,710,000$10,710,000$0$1,400,868$1,400,86813%$140,087
505-100Structural steel$6,783,000$314,616$7,097,616$1,576,369$938,767$2,515,13635%$251,514
607-500Roofing and waterproofing$3,213,000$3,213,000$553,921$444,679$998,60031%$99,860
708-400Curtain wall and glazing$8,568,000$8,568,000$963,043$1,185,811$2,148,85425%$214,885
809-250Drywall and framing$4,998,000$4,998,000$261,895$691,723$953,61819%$95,362
909-650Flooring and finishes$3,927,000$3,927,000$0$513,652$513,65213%$51,365
1015-400Plumbing$4,284,000$4,284,000$995,602$592,906$1,588,50737%$158,851
1115-700HVAC$6,783,000$6,783,000$1,169,389$938,767$2,108,15631%$210,816
1216-100Electrical$5,355,000$5,355,000$601,902$741,132$1,343,03425%$134,303
1321-100Fire protection$1,428,000$1,428,000$74,827$197,635$272,46219%$27,246
Totals$71,400,000$1,178,477$72,578,477$7,836,721$9,770,519$17,607,240$024%$1,760,724

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 13Jan 20, 2026
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Jan 23, 2026
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1Feb 28, 2026