Application 11

Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Jul 16, 2026 · Certified

Completed to date

$64,161,111

Stored materials

$0

Retainage withheld

$6,416,111

Retainage required

$6,416,111

Due this application

$1,324,913

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$4,711,115$121,951$4,833,06697%$483,307
202-200Sitework and excavation$3,927,000$338,921$4,265,921$3,465,970$95,819$3,561,78983%$356,179
303-300Concrete, foundations$6,426,000$524,940$6,950,940$5,286,028$156,794$5,442,82278%$544,282
403-330Concrete, superstructure$10,710,000$10,710,000$8,167,446$261,324$8,428,77079%$842,877
505-100Structural steel$6,783,000$314,616$7,097,616$6,783,000$0$6,783,00096%$678,300
607-500Roofing and waterproofing$3,213,000$3,213,000$3,028,574$78,397$3,106,97197%$310,697
708-400Curtain wall and glazing$8,568,000$8,568,000$7,562,117$209,059$7,771,17691%$777,118
809-250Drywall and framing$4,998,000$4,998,000$4,111,355$121,951$4,233,30685%$423,331
909-650Flooring and finishes$3,927,000$3,927,000$2,994,730$95,819$3,090,54979%$309,055
1015-400Plumbing$4,284,000$4,284,000$4,284,000$0$4,284,000100%$428,400
1115-700HVAC$6,783,000$6,783,000$6,393,656$165,505$6,559,16197%$655,916
1216-100Electrical$5,355,000$5,355,000$4,726,323$130,662$4,856,98591%$485,699
1321-100Fire protection$1,428,000$1,428,000$1,174,673$34,843$1,209,51685%$120,952
Totals$71,400,000$1,178,477$72,578,477$62,688,986$1,472,125$64,161,111$088%$6,416,111

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app11.pdf p.1 of 4Jul 19, 2026
conditional_waiverwaiver_cond_app11.pdf p.1 of 1Jul 22, 2026