Brickell Bay Tower · C-BRK-2201-01 · period ending Jul 31, 2025 · Paid

Completed to date

$10,753,683

Stored materials

$0

Retainage withheld

$1,075,368

Retainage required

$1,075,368

Due this application

$4,600,450

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$982,847$900,675$1,883,52218%$188,352
202-200Sitework and excavation$8,167,500$8,167,500$12,660$707,673$720,3339%$72,033
303-300Concrete, foundations$13,365,000$13,365,000$0$0$00%$0
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$0$0$00%$0
505-100Structural steel$14,107,500$14,107,500$1,707,008$788,609$2,495,61718%$249,562
607-500Roofing and waterproofing$6,682,500$6,682,500$407,633$373,552$781,18412%$78,118
708-400Curtain wall and glazing$17,820,000$17,820,000$17,820$996,138$1,013,9586%$101,396
809-250Drywall and framing$10,395,000$10,395,000$0$0$00%$0
909-650Flooring and finishes$8,167,500$8,167,500$0$0$00%$0
1015-400Plumbing$8,910,000$830,266$9,740,266$1,078,110$498,069$1,576,17916%$157,618
1115-700HVAC$14,107,500$662,148$14,769,648$860,558$788,609$1,649,16711%$164,917
1216-100Electrical$11,137,500$11,137,500$11,138$622,586$633,7246%$63,372
1321-100Fire protection$2,970,000$2,970,000$0$0$00%$0
Totals$148,500,000$3,197,001$151,697,001$5,077,772$5,675,911$10,753,683$07%$1,075,368

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 10Aug 3, 2025
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Aug 6, 2025
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Sep 11, 2025