Drawcheck
Meridian Builders

Application 12

Wynwood Yards Mixed Use · C-WYN-2304-03 · period ending Aug 15, 2026 · Submitted

Completed to date

$64,885,107

Stored materials

$0

Retainage withheld

$6,488,511

Retainage required

$6,488,511

Due this application

$651,596

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$4,998,000$4,998,000$4,833,066$59,976$4,893,04298%$489,304
202-200Sitework and excavation$3,927,000$338,921$4,265,921$3,561,789$47,124$3,608,91385%$360,891
303-300Concrete, foundations$6,426,000$524,940$6,950,940$5,442,822$77,112$5,519,93479%$551,993
403-330Concrete, superstructure$10,710,000$10,710,000$8,428,770$128,520$8,557,29080%$855,729
505-100Structural steel$6,783,000$314,616$7,097,616$6,783,000$0$6,783,00096%$678,300
607-500Roofing and waterproofing$3,213,000$3,213,000$3,106,971$38,556$3,145,52798%$314,553
708-400Curtain wall and glazing$8,568,000$8,568,000$7,771,176$102,816$7,873,99292%$787,399
809-250Drywall and framing$4,998,000$4,998,000$4,233,306$59,976$4,293,28286%$429,328
909-650Flooring and finishes$3,927,000$3,927,000$3,090,549$47,124$3,137,67380%$313,767
1015-400Plumbing$4,284,000$4,284,000$4,284,000$0$4,284,000100%$428,400
1115-700HVAC$6,783,000$6,783,000$6,559,161$81,396$6,640,55798%$664,056
1216-100Electrical$5,355,000$5,355,000$4,856,985$64,260$4,921,24592%$492,125
1321-100Fire protection$1,428,000$1,428,000$1,209,516$17,136$1,226,65286%$122,665
Totals$71,400,000$1,178,477$72,578,477$64,161,111$723,996$64,885,107$089%$6,488,511

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app12.pdf p.1 of 12Aug 18, 2026
conditional_waiverwaiver_cond_app12.pdf p.1 of 1Aug 21, 2026