Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Sep 19, 2025 · Paid

Completed to date

$187,846

Stored materials

$0

Retainage withheld

$9,392

Retainage required

$9,392

Due this application

$178,454

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$19,024$19,0241%$951
216-100Electrical$1,995,536$1,995,536$0$00%$0
315-700HVAC$2,527,679$2,527,679$0$00%$0
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$0$00%$0
501-100General conditions$1,862,500$1,862,500$135,963$135,9637%$6,798
605-100Structural steel$2,527,679$2,527,679$32,860$32,8601%$1,643
721-100Fire protection$532,143$39,615$571,758$0$00%$0
Totals$14,900,000$396,515$15,296,515$0$187,846$187,846$01%$9,392

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 8Sep 22, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1Sep 25, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1Oct 31, 2025