HighSTORED-NOT-PERMITTEDStored materials billed under a contract that forbids them$74,500
$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials
The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.
Remedy Remove the stored materials line from the application and pay installed work only.
claimed $74,500supported not permittedcontinuation line 5 (01-100)