Drawcheck
Delmar Mechanical

Application 2

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Oct 19, 2025 · Paid

Completed to date

$330,674

Stored materials

$74,500

Retainage withheld

$20,259

Retainage required

$20,259

Due this application

$206,461

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$19,024$35,707$54,7313%$2,737
216-100Electrical$1,995,536$1,995,536$0$0$00%$0
315-700HVAC$2,527,679$2,527,679$0$0$00%$0
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$0$0$00%$0
501-100General conditions$1,862,500$1,862,500$135,963$45,445$181,408$74,50010%$12,795
605-100Structural steel$2,527,679$2,527,679$32,860$61,675$94,5354%$4,727
721-100Fire protection$532,143$39,615$571,758$0$0$00%$0
Totals$14,900,000$396,515$15,296,515$187,846$142,827$330,674$74,5002%$20,259

Exceptions on this application

HighSTORED-NOT-PERMITTEDStored materials billed under a contract that forbids them$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

Remedy Remove the stored materials line from the application and pay installed work only.

claimed $74,500supported not permittedcontinuation line 5 (01-100)

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app02.pdf p.1 of 13Oct 22, 2025
conditional_waiverwaiver_cond_app02.pdf p.1 of 1Oct 25, 2025
supplier_invoiceinvoice_app02.pdf p.1 of 3$43,902Oct 23, 2025
unconditional_waiverwaiver_uncond_app02.pdf p.1 of 1Nov 30, 2025