Application 3

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Nov 18, 2025 · Paid

Completed to date

$675,010

Stored materials

$74,500

Retainage withheld

$37,475

Retainage required

$37,476

Due this application

$327,120

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$54,731$70,097$124,8278%$6,241
216-100Electrical$1,995,536$1,995,536$0$50,487$50,4873%$2,524
315-700HVAC$2,527,679$2,527,679$0$0$00%$0
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$0$0$00%$0
501-100General conditions$1,862,500$1,862,500$181,408$89,214$270,621$74,50015%$17,256
605-100Structural steel$2,527,679$2,527,679$94,535$121,076$215,6119%$10,781
721-100Fire protection$532,143$39,615$571,758$0$13,463$13,4632%$673
Totals$14,900,000$396,515$15,296,515$330,674$344,336$675,010$74,5004%$37,475

Exceptions on this application

HighSTORED-NOT-PERMITTEDStored materials billed under a contract that forbids them$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

Remedy Remove the stored materials line from the application and pay installed work only.

claimed $74,500supported not permittedcontinuation line 5 (01-100)

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 7Nov 21, 2025
conditional_waiverwaiver_cond_app03.pdf p.1 of 1Nov 24, 2025
supplier_invoiceinvoice_app03.pdf p.1 of 2$43,902Nov 22, 2025
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1Dec 30, 2025