Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Dec 18, 2025 · Paid

Completed to date

$1,537,467

Stored materials

$0

Retainage withheld

$76,873

Retainage required

$76,873

Due this application

$748,559

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$124,827$127,462$252,28916%$12,614
216-100Electrical$1,995,536$1,995,536$50,487$173,811$224,29811%$11,215
315-700HVAC$2,527,679$2,527,679$0$132,450$132,4505%$6,623
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$0$0$00%$0
501-100General conditions$1,862,500$1,862,500$270,621$162,224$432,84523%$21,642
605-100Structural steel$2,527,679$2,527,679$215,611$220,161$435,77217%$21,789
721-100Fire protection$532,143$39,615$571,758$13,463$46,350$59,81310%$2,991
Totals$14,900,000$396,515$15,296,515$675,010$862,457$1,537,467$010%$76,873

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 8Dec 21, 2025
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Dec 24, 2025
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Jan 29, 2026