Delmar Mechanical

Application 5

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Jan 17, 2026 · Paid

Completed to date

$3,569,295

Stored materials

$0

Retainage withheld

$178,465

Retainage required

$178,465

Due this application

$1,930,236

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$252,289$202,534$454,82329%$22,741
216-100Electrical$1,995,536$1,995,536$224,298$276,182$500,48025%$25,024
315-700HVAC$2,527,679$2,527,679$132,450$349,831$482,28119%$24,114
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$0$522,032$522,03212%$26,102
501-100General conditions$1,862,500$1,862,500$432,845$257,770$690,61537%$34,531
605-100Structural steel$2,527,679$2,527,679$435,772$349,831$785,60331%$39,280
721-100Fire protection$532,143$39,615$571,758$59,813$73,649$133,46123%$6,673
Totals$14,900,000$396,515$15,296,515$1,537,467$2,031,828$3,569,295$023%$178,465

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 14Jan 20, 2026
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Jan 23, 2026
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1Feb 28, 2026