Drawcheck
← Delmar Mechanical

Application 6

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Feb 16, 2026 · Paid

Completed to date

$6,239,375

Stored materials

$0

Retainage withheld

$311,969

Retainage required

$311,969

Due this application

$2,536,576

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$454,823$262,240$717,063—46%$35,853
216-100Electrical$1,995,536—$1,995,536$500,480$357,600$858,080—43%$42,904
315-700HVAC$2,527,679—$2,527,679$482,281$452,960$935,241—37%$46,762
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$522,032$715,200$1,237,232—29%$61,862
501-100General conditions$1,862,500—$1,862,500$690,615$333,760$1,024,375—55%$51,219
605-100Structural steel$2,527,679—$2,527,679$785,603$452,960$1,238,563—49%$61,928
721-100Fire protection$532,143$39,615$571,758$133,461$95,360$228,821—40%$11,441
Totals$14,900,000$396,515$15,296,515$3,569,295$2,670,080$6,239,375$041%$311,969

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app06.pdf p.1 of 10—Feb 19, 2026
conditional_waiverwaiver_cond_app06.pdf p.1 of 1—Feb 22, 2026
unconditional_waiverwaiver_uncond_app06.pdf p.1 of 1—Mar 30, 2026