Drawcheck
← Delmar Mechanical

Application 7

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Mar 18, 2026 · Paid

Completed to date

$8,909,455

Stored materials

$0

Retainage withheld

$445,473

Retainage required

$445,473

Due this application

$2,536,576

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$717,063$262,240$979,303—62%$48,965
216-100Electrical$1,995,536—$1,995,536$858,080$357,600$1,215,680—61%$60,784
315-700HVAC$2,527,679—$2,527,679$935,241$452,960$1,388,201—55%$69,410
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$1,237,232$715,200$1,952,432—46%$97,622
501-100General conditions$1,862,500—$1,862,500$1,024,375$333,760$1,358,135—73%$67,907
605-100Structural steel$2,527,679—$2,527,679$1,238,563$452,960$1,691,523—67%$84,576
721-100Fire protection$532,143$39,615$571,758$228,821$95,360$324,181—57%$16,209
Totals$14,900,000$396,515$15,296,515$6,239,375$2,670,080$8,909,455$058%$445,473

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app07.pdf p.1 of 4—Mar 21, 2026
conditional_waiverwaiver_cond_app07.pdf p.1 of 1—Mar 24, 2026
unconditional_waiverwaiver_uncond_app07.pdf p.1 of 1—Apr 29, 2026