Application 8

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Apr 17, 2026 · Paid

Completed to date

$10,971,615

Stored materials

$0

Retainage withheld

$548,581

Retainage required

$548,581

Due this application

$1,959,052

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$979,303$202,534$1,181,83675%$59,092
216-100Electrical$1,995,536$1,995,536$1,215,680$276,182$1,491,86375%$74,593
315-700HVAC$2,527,679$2,527,679$1,388,201$349,831$1,738,03269%$86,902
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$1,952,432$552,364$2,504,79659%$125,240
501-100General conditions$1,862,500$1,862,500$1,358,135$257,770$1,615,90587%$80,795
605-100Structural steel$2,527,679$2,527,679$1,691,523$349,831$2,041,35381%$102,068
721-100Fire protection$532,143$39,615$571,758$324,181$73,649$397,83070%$19,892
Totals$14,900,000$396,515$15,296,515$8,909,455$2,062,160$10,971,615$072%$548,581

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app08.pdf p.1 of 12Apr 20, 2026
conditional_waiverwaiver_cond_app08.pdf p.1 of 1Apr 23, 2026
unconditional_waiverwaiver_uncond_app08.pdf p.1 of 1May 29, 2026