Drawcheck
Delmar Mechanical

Application 9

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending May 17, 2026 · Paid

Completed to date

$12,269,405

Stored materials

$0

Retainage withheld

$613,470

Retainage required

$613,470

Due this application

$1,232,901

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$1,181,836$127,462$1,309,29883%$65,465
216-100Electrical$1,995,536$1,995,536$1,491,863$173,811$1,665,67483%$83,284
315-700HVAC$2,527,679$2,527,679$1,738,032$220,161$1,958,19377%$97,910
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$2,504,796$347,622$2,852,41967%$142,621
501-100General conditions$1,862,500$1,862,500$1,615,905$162,224$1,778,12995%$88,906
605-100Structural steel$2,527,679$2,527,679$2,041,353$220,161$2,261,51489%$113,076
721-100Fire protection$532,143$39,615$571,758$397,830$46,350$444,18078%$22,209
Totals$14,900,000$396,515$15,296,515$10,971,615$1,297,790$12,269,405$080%$613,470

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app09.pdf p.1 of 6May 20, 2026
conditional_waiverwaiver_cond_app09.pdf p.1 of 1May 23, 2026
unconditional_waiverwaiver_uncond_app09.pdf p.1 of 1Jun 28, 2026