Brickell Bay Tower · C-BRK-2201-01 · period ending Aug 30, 2025 · Paid

Completed to date

$23,622,704

Stored materials

$0

Retainage withheld

$2,362,270

Retainage required

$2,362,270

Due this application

$11,582,119

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000$10,395,000$1,883,522$1,445,269$3,328,79132%$332,879
202-200Sitework and excavation$8,167,500$8,167,500$720,333$1,135,568$1,855,90123%$185,590
303-300Concrete, foundations$13,365,000$13,365,000$0$1,793,984$1,793,98413%$179,398
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$0$592,515$592,5152%$59,252
505-100Structural steel$14,107,500$14,107,500$2,495,617$1,265,443$3,761,06027%$376,106
607-500Roofing and waterproofing$6,682,500$6,682,500$781,184$599,420$1,380,60521%$138,060
708-400Curtain wall and glazing$17,820,000$17,820,000$1,013,958$1,598,454$2,612,41215%$261,241
809-250Drywall and framing$10,395,000$10,395,000$0$900,207$900,2079%$90,021
909-650Flooring and finishes$8,167,500$8,167,500$0$217,256$217,2563%$21,726
1015-400Plumbing$8,910,000$830,266$9,740,266$1,576,179$799,227$2,375,40624%$237,541
1115-700HVAC$14,107,500$662,148$14,769,648$1,649,167$1,265,443$2,914,61020%$291,461
1216-100Electrical$11,137,500$11,137,500$633,724$999,034$1,632,75815%$163,276
1321-100Fire protection$2,970,000$2,970,000$0$257,202$257,2029%$25,720
Totals$148,500,000$3,197,001$151,697,001$10,753,683$12,869,021$23,622,704$016%$2,362,270

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 14Sep 2, 2025
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Sep 5, 2025
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1Oct 11, 2025