Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Jun 16, 2026 · Paid

Completed to date

$12,978,273

Stored materials

$0

Retainage withheld

$648,914

Retainage required

$648,914

Due this application

$673,424

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$1,309,298$70,097$1,379,39488%$68,970
216-100Electrical$1,995,536$1,995,536$1,665,674$95,586$1,761,26088%$88,063
315-700HVAC$2,527,679$2,527,679$1,958,193$121,076$2,079,26882%$103,963
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$2,852,419$191,172$3,043,59172%$152,180
501-100General conditions$1,862,500$1,862,500$1,778,129$84,371$1,862,500100%$93,125
605-100Structural steel$2,527,679$2,527,679$2,261,514$121,076$2,382,59094%$119,129
721-100Fire protection$532,143$39,615$571,758$444,180$25,490$469,66982%$23,483
Totals$14,900,000$396,515$15,296,515$12,269,405$708,867$12,978,273$085%$648,914

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app10.pdf p.1 of 7Jun 19, 2026
conditional_waiverwaiver_cond_app10.pdf p.1 of 1Jun 22, 2026
unconditional_waiverwaiver_uncond_app10.pdf p.1 of 1Jul 28, 2026