Drawcheck
Delmar Mechanical

Application 11

Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Jul 16, 2026 · Certified

Completed to date

$13,296,388

Stored materials

$0

Retainage withheld

$664,819

Retainage required

$664,819

Due this application

$302,209

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$1,379,394$35,707$1,415,10190%$70,755
216-100Electrical$1,995,536$1,995,536$1,761,260$48,691$1,809,95191%$90,498
315-700HVAC$2,527,679$2,527,679$2,079,268$61,675$2,140,94485%$107,047
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$3,043,591$97,382$3,140,97374%$157,049
501-100General conditions$1,862,500$1,862,500$1,862,500$0$1,862,500100%$93,125
605-100Structural steel$2,527,679$2,527,679$2,382,590$61,675$2,444,26597%$122,213
721-100Fire protection$532,143$39,615$571,758$469,669$12,984$482,65484%$24,133
Totals$14,900,000$396,515$15,296,515$12,978,273$318,115$13,296,388$087%$664,819

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app11.pdf p.1 of 7Jul 19, 2026
conditional_waiverwaiver_cond_app11.pdf p.1 of 1Jul 22, 2026