Wynwood Yards Mixed Use · C-WYN-2304-04 · period ending Aug 15, 2026 · Submitted

Completed to date

$13,452,838

Stored materials

$0

Retainage withheld

$672,642

Retainage required

$672,642

Due this application

$148,627

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
102-200Sitework and excavation$1,463,393$110,451$1,573,843$1,415,101$17,561$1,432,662—91%$71,633
216-100Electrical$1,995,536—$1,995,536$1,809,951$23,946$1,833,897—92%$91,695
315-700HVAC$2,527,679—$2,527,679$2,140,944$30,332$2,171,276—86%$108,564
403-330Concrete, superstructure$3,991,071$246,449$4,237,521$3,140,973$47,893$3,188,866—75%$159,443
501-100General conditions$1,862,500—$1,862,500$1,862,500$0$1,862,500—100%$93,125
605-100Structural steel$2,527,679—$2,527,679$2,444,265$30,332$2,474,597—98%$123,730
721-100Fire protection$532,143$39,615$571,758$482,654$6,386$489,039—86%$24,452
Totals$14,900,000$396,515$15,296,515$13,296,388$156,450$13,452,838$088%$672,642

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app12.pdf p.1 of 5—Aug 18, 2026
conditional_waiverwaiver_cond_app12.pdf p.1 of 1—Aug 21, 2026